Sewage construction February 2024

by | Feb 28, 2024 | Events, Our Projects

In February, we’ve constructed a new sewage system and toliet at the Oji River Settlement.

We recieved the constuction materials.

We dug and excavated the soil, create a manhole ready for construction. We then pulled down the cerment mixing and lay bricks for the framework. Once it’s dried, we plastered the wall and floor.

Then we lay the pipe work, complete and sealed the system.

We completed the work by installing the toliet and handwash basin and painted the walls.